Explanation: Total 8 steps, 3 days, max 2 steps per slot (Morning/Afternoon). J must be on Day 2. K and M must be simultaneous (2 slots). M and O must be before J. If J is Day 2 Morning (1 slot), then the tasks before J (M and O) must be completed before Day 2 Morning. The earliest time for M and O to be completed is Day 1. Since K and M must be simultaneous (2 slots) and must be done by Day 1, and O must also be done by Day 1 (1 slot). This means K, M, and O (3 steps, 3 slots) must be done on Day 1. The remaining 5 steps (H, L, P, S, 1 more slot) must be done in the remaining 3 slots on Day 1 (1 slot) and Day 2 (3 slots). The minimum 3 tasks (K, M, O) **must** be done on Day 1. The remaining Day 1 slot must be filled by H, L, P, or S. The question asks what **must** be performed on the first day. The required steps (K, M, O) before J must be done on Day 1. Since K is an option and K is part of the mandatory group (K, M, O) on Day 1, K **must** be performed on the first day.